Project Title | Efficient Service Life Extension of Bridges through Risk-based Life-cycle Management and High-performance Construction Materials: Emphasis on Corrosion-resistant Steel |
University | Lehigh University |
Principal Investigator(s) | Dan M. Frangopol |
PI Contact Information | Dmf206@lehigh.edu |
Funding Source(s) and Amounts Provided (by each agency or organization) | Lehigh-- Federal Funds, $64,644.80, Match, $69,238.68 |
Total Project Cost | $133,883.48 Federal $64,644.80, Match Amount $69,238.68 |
Start and End Dates | 3/1/19—3/1/20 (extended through 9/30/20) |
Brief Description of Research Project | The main objective of this project is to establish an effective life-cycle bridge management framework for novel intervention actions based on high-performance construction materials. This objective will be primarily achieved by (a) risk-based ranking of bridge criticality, (b) life-cycle risk assessment of bridges repaired with high-performance construction materials, and (c) risk-informed service life extension considering operational dependency of intervention actions. |